Underpinning Subcommittee Update
José Busquets, Bracken Engineering
The underpinning subcommittee is currently in the progress of creating an update to the previously issued Underpinning
Guidelines (UP-08) published by FAS3 in 2008. These guidelines will be geared towards the application of different underpinning systems
(helical piles, driven piles, drilled piers, etc.) and how each system performs in specific applications. The revisions will also address what
information needs to be provided in the shop drawing submittal from the contractor to the Engineer of Record, minimum guidelines for load
testing an underpin bracket assembly, how soil profiles affect the size of pin piles, calibration of field equipment, and the evolvement of
underpinning cast-in-place slabs. The underpinning subcommittee is working towards completing the updates to the UP-08 by the fourth quarter of
this year.
|